Location

Essex

Services

N/A

Size

280 m2

Project Length

10 weeks

The Brief

To provide extra space for 3 separate classrooms and toilets with a link corridor to the existing school.

The Solution

The Qube proposed and executed a design and build package which allowed a modular unit to be built on-site, with minimal disruption to the school.

The Outcome

A new extension with a seamless transition into the school’s existing building. The new space has allowed the school to accept more children and the teachers and children love their new learning spaces.